Building News

Our Lady of Guadalupe Church

Our Professionals
Our Parish Site
Our Project
Capital Campaign

Construction Progress

Past Two Weeks

  • Continue with under slab rough in.

  • Completed footings.

  • Continue with backfill of footings.

  • Continue with block walls.

  • Start storm  water pipe at Rt. 413 entrance.

  • Prep for slab on grade and pour.

 

Two Week Look Ahead

  • Pour slab on grade.

  • Continue with block walls.

  • Continue with setting concrete.

  • Continue with site work and start paving.

  • Connect water line into building.

  • Start duct work in basement.

 

Updated: 7/8/10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 