Construction Progress |
|
Past Two Weeks
-
Continue with under slab rough in.
-
Completed footings.
-
Continue with backfill of footings.
-
Continue with block walls.
-
Start storm water pipe at Rt. 413 entrance.
-
Prep for slab on grade and pour.
|
|
Two Week Look Ahead
-
Pour slab on grade.
-
Continue with block walls.
-
Continue with setting concrete.
-
Continue with site work and start paving.
-
Connect water line into building.
-
Start duct work in basement.
|
|