Photos

Home
About OLG
Building News
Bulletins
Catholic Links
Contacts
Map and Directions
Mass Schedule
Ministry Schedules
Monthly Calendar
Organizations
Parish Staff
Parish News
Photos
P.R.E.P.
Safe Environment
Youth Group
About OLG
Building News
Bulletins
Catholic Links
Contacts
Map and Directions
Mass Schedule
Ministry Schedules
Monthly Calendar
Organizations
Parish Staff
Parish News
Photos
P.R.E.P.
Safe Environment
Youth Group
About OLG
About OLG
Building News
Bulletins
Catholic Links
History
Map and Directions
Mass Schedule
Ministry Schedules
Monthly Calendar
Organizations
Parish News
Parish Staff
Photos
P.R.E.P.
Safe Environment
Youth Group

Click on the images below to view parish events albums

Click to view my photos OLG July 24, 2010 Update Church building steel framework nearing completion. Views from several angles around perimeter of show extent of work being done.
Click to view my photos OLG July 22, 2010 Update Installation of the steel superstructure is moving along quite quickly now. Area where cupola will be installed is almost complete. Preparation for the stone facade is underway. Views from the parking area and Cold Spring Creamery Road show size and scale of Church building.
Click to view my photos OLG July 17, 2010 Update Walls have been built along entrance to Narthex and adjoining area along the perimeter of the Church. Concrete pads for the columns in front of the Church are now in place. The concrete slab in main area of the Church has bee poured and new steel has been brought to the site. The crane used to install the steel is being assembled and steel girders and beams will be installed next week. HVAC ducts in the basement are ready for installation.
Click to view my photos OLG July 7, 2010 Update Construction of Church is rapidly showing progress. Walls on both sides of building are nearing completion and size and scale of entire building is becoming more apparent. New steel construction should begin this coming week which will give even greater idea of what Church building will look like. Area over HVAC has been graded and grid laid for concrete pad which should be poured next week.
Click to view my photos OLG New Chapel You can save these photos after viewing them by creating a free Kodak Gallery account.
Click to view my photos OLG June 29, 2010 - UPDATE Progress continues at the Church building site with the block walls being erected on both sides of the building, back filling around HVAC ducts and grading in preparation for the concrete slab floor of the Church. Footings are in place for the Church entrance and steel should begin to be installed within the next two weeks. Grading and gravel bed in the parking lots are nearing completion, as is the landscaping. Overhead view shows the outline of the Church and Chapel more clearly since the grading continues and the block walls are being erected.
Click to view my photos OLG June 19, 2010 - UPDATE Landscaping is nearing completion around parking area as well as along the open space.  Grading around foundation front and rear of the Church building is being completed. As soon as the installation of the HVAC conduits is completed the area within the Church foundation will be graded in preparation for the concrete foundation to be poured. The walls of the Church in the area of the Narthex are being constructed, connecting with the walls to the right of the entrance to the Narthex that have been visible in previous photos.
Click to view my photos OLG June 10, 2010 - UPDATE Cement has been poured for flooring over basement in Nathex. Landscaping is being installed throughout the property. Back fill around basement walls is in progress and grading in preparation for the concrete slab for the Church is nearing completion.
Click to view my photos

OLG June 5, 2010 - UPDATE

Steel floor is completed and awaiting concrete to be applied this coming week. Landscaping is being done along walkway on Cold Spring Creamery Road. Concrete path has been laid between parking areas.
Click to view my photos

OLG May 26, 2010 -

Day 3 UPDATE

Steel floor is nearing completion over the basement. Concrete will be applied if the weather cooperates.

Click to view my photos   

OLG Church Steel Installation Day 2 May 26, 2010 Beams in place over front entrance, floor beams installed and ready for flooring. Basement views show HVAC units installed on pads. Conduits for HVAC in process of being placed underground. Water resistant shield completed around entire exterior basement walls.  In background workmen are grading and preparing parking areas for some concrete walkways and asphalt

Click to view my photos

OLG Church Steel Installation 

May 25, 2010

 

This is the beginning of the installation of the steel inside and above the basement. The formation of the entry way to the Church can now be visualized. These photos were taken between 10 AM and noon on May 25. The steel installation will continue this afternoon and for the next two days. In addition, the work continues in many other areas of the site, as can be seen throughout the photos.  These photos show the installation of the beams in the basement area creating the floor area where we will enter the Church into the Narthex.
Click to view my photosOLG Church Construction Site May 22, 2010
Click to view my photosOLG Church Construction Site May 14, 2010
Click to view my photosOLG Church Construction Site May 8, 2010
Click to view my photosOLG Church Construction Site April 29, 2010
Click to view my photosOLG Church Construction Site April 18, 2010
Click to view my photosOLG Town Hall Meeting April 11, 2010
Click to view my photosOLG Easter Vigil 2010
Click to view my photosOLG Easter 2010 Altar Decorations

Click to view my photos OLG Church Construction Site April 3, 2010

Click to view my photos OLG Church Construction Site March 7, 2010

Click to view my photos Christmas 2009 Altar Decorations

Click to view my photos     Our Lady of Guadalupe Feast Day Dec 12, 2009
Click to view my photos   Thanksgiving Mass Nov 2009

Click to view my photos     OLG -  Long Awaited Update - November 21, 2009

Click to view my photos     OLG - Humble Beginnings at Hollyberry Square

Click to view my photos     Youth Group - Haunted Hay Ride - November 1, 2009

Click to view my photos     Youth Group - Pumpkin Decorating Contest - October 11, 2009
    OLG Chapel - First Benediction - October 2, 2009 

     OLG UPDATE - September 17, 2009.  Excavation of Church Basement 

     OLG UPDATE - September 11, 2009. Removal Of The Farmhouse

     OLG UPDATE - August 18, 2009

    Construction Begins On Our Parish

     First Mass at OLG Chapel

     First Baptism On Our New Site

     Fr. Gentili's Installation July 17, 2009

 

counter for blogger
          This page was last updated 07/24/10