 |
OLG July
24, 2010 Update | Church building steel framework nearing completion. Views
from several angles around perimeter of show extent of work being done. |
 |
OLG July
22, 2010 Update | Installation of the steel superstructure is moving along
quite quickly now. Area where cupola will be installed is almost
complete. Preparation for the stone facade is underway. Views from the
parking area and Cold Spring Creamery Road show size and scale of Church
building. |
 |
OLG July 17, 2010 Update | Walls have been built along entrance to Narthex and
adjoining area along the perimeter of the Church. Concrete pads for the
columns in front of the Church are now in place. The concrete slab in
main area of the Church has bee poured and new steel has been brought to
the site. The crane used to install the steel is being assembled and
steel girders and beams will be installed next week. HVAC ducts in the
basement are ready for installation. |
 |
OLG July 7, 2010 Update | Construction of Church is rapidly showing progress. Walls
on both sides of building are nearing completion and size and scale of
entire building is becoming more apparent. New steel construction should
begin this coming week which will give even greater idea of what Church
building will look like. Area over HVAC has been graded and grid laid
for concrete pad which should be poured next week. |
 |
OLG New Chapel | You can save these photos after viewing them by creating
a free Kodak Gallery account. |
 |
OLG June
29, 2010 - UPDATE | Progress continues at the Church building site with the
block walls being erected on both sides of the building, back filling
around HVAC ducts and grading in preparation for the concrete slab floor
of the Church. Footings are in place for the Church entrance and steel
should begin to be installed within the next two weeks. Grading and
gravel bed in the parking lots are nearing completion, as is the
landscaping. Overhead view shows the outline of the Church and Chapel
more clearly since the grading continues and the block walls are being
erected. |
 |
OLG June
19, 2010 - UPDATE | Landscaping is nearing completion around parking area as
well as along the open space. Grading around foundation front and
rear of the Church building is being completed. As soon as the
installation of the HVAC conduits is completed the area within the
Church foundation will be graded in preparation for the concrete
foundation to be poured. The walls of the Church in the area of the
Narthex are being constructed, connecting with the walls to the right of
the entrance to the Narthex that have been visible in previous photos. |
 |
OLG June
10, 2010 - UPDATE | Cement has been poured for flooring over basement in
Nathex. Landscaping is being installed throughout the property. Back
fill around basement walls is in progress and grading in preparation for
the concrete slab for the Church is nearing completion. |
 |
OLG June 5, 2010 - UPDATE | Steel floor is completed and awaiting concrete to be
applied this coming week. Landscaping is being done along walkway on
Cold Spring Creamery Road. Concrete path has been laid between parking
areas. |
 |
OLG May 26, 2010 -
Day 3 UPDATE | Steel floor is nearing completion over the basement.
Concrete will be applied if the weather cooperates. |
|
|
OLG Church Steel
Installation Day 2 May 26, 2010 | Beams in place over front entrance, floor beams installed
and ready for flooring. Basement views show HVAC units installed on
pads. Conduits for HVAC in process of being placed underground. Water
resistant shield completed around entire exterior basement walls.
In background workmen are grading and preparing parking areas for some
concrete walkways and asphalt |
|
 | OLG Church Steel Installation
May 25, 2010
| This is the beginning of the installation of the steel
inside and above the basement. The formation of the entry way to the
Church can now be visualized. These photos were taken between 10 AM and
noon on May 25. The steel installation will continue this afternoon and
for the next two days. In addition, the work continues in many other
areas of the site, as can be seen throughout the photos. These
photos show the installation of the beams in the basement area creating
the floor area where we will enter the Church into the Narthex. |
OLG Church Construction Site May 22, 2010 |
OLG Church Construction Site May 14, 2010 |
OLG Church Construction Site May 8, 2010 |
OLG Church Construction Site April 29, 2010 |
OLG Church Construction Site April 18, 2010 |
OLG Town Hall Meeting April 11, 2010 |
OLG Easter Vigil 2010 |
OLG Easter 2010 Altar Decorations |
| OLG Church Construction Site April 3, 2010 |
| OLG Church Construction Site March 7, 2010 |
| Christmas 2009 Altar Decorations |
Our Lady of Guadalupe Feast Day Dec 12, 2009 |
Thanksgiving Mass Nov 2009 |
| OLG - Long Awaited Update - November 21, 2009 |
| OLG - Humble Beginnings at Hollyberry Square |
| Youth Group - Haunted Hay Ride - November 1, 2009 |
Youth Group - Pumpkin Decorating Contest - October 11, 2009 |
OLG Chapel - First Benediction - October 2, 2009 |
|  OLG UPDATE - September 17, 2009. Excavation of Church Basement |
|  OLG UPDATE - September 11, 2009. Removal Of The Farmhouse |
|  OLG UPDATE - August 18, 2009 |
|   Construction Begins On Our Parish |
First Mass at OLG Chapel |
|  First Baptism On Our New Site |
|   Fr. Gentili's Installation July 17, 2009 |